Solar Tower, Seville, Spain

 

Key Data:

Construction completed
PS10 was completed at the end of 2006. Work commenced on PS20 during the second half of 2006
Start of Operation
March 2007 for PS10
Output
300 MW solar tower
Plant Type
Solar heating
Estimated Completion
2013
Location
near Seville, Spain.
Estimated Investment
around €1,200m
Employment
1,000 manufacturing/construction jobs, 300 full-time service and maintenance jobs

Key Players:

Plant Owner and Constructor
Solucar
Co-Operating Institutions
Ciemat, the IDEA, University of Seville



Home
New On This Site
Products & Services
Company A-Z
Industry Projects
Special Reports
Videos
White Papers
Industry News
Gallery
Events & Exhibitions
Newsletter Sign-Up
Advertise With Us
About Us
Client Area


RSS What is RSS
The website for the power industry