Key Data:
Construction completed
PS10 was completed at the end of 2006. Work commenced on PS20 during the second half of 2006
Start of Operation
March 2007 for PS10
Output
300 MW solar tower
Location
near Seville, Spain.
Estimated Investment
around €1,200m
Employment
1,000 manufacturing/construction jobs, 300 full-time service and maintenance jobs
Key Players:
Plant Owner and Constructor
Solucar
Co-Operating Institutions
Ciemat, the IDEA, University of Seville