Bursa CCGT Power Plant, Turkey

 

Key Data:

Order year
1995
Output
1,400MW
Plant type
CCGT
Location
Bursa, Anatolia, Turkey
Estimated investment
$5.8 million
Completion
1999

Key Players:

Sponsor
Turkish Electricity Generation and Transmission Corp (TEAS)
Lead equipment supplier
Mitsubishi / Itochu / Enka consortium
Construction
Enka
Construction management and technical direction
Shanahan Engineering
Fuel supply
Gazexport

Plant Details:

Gas units
4 x 239MW
Steam units
2 x 237.5MW
Fuel
Natural gas