Key Data:
Initial Building Period
Summer and Autumn 2003
Grid Connection
November 2003
Announcement of Expansion
December 2004
Location
Near Dunbar, approximately 50km south of Edinburgh
Key Players:
Plant Owner
Crystal Rig Windfarm Ltd. a subsidiary of Fred Olsen Renewables Ltd., Oslo, Norway
Power Utility
Scottish Power
Project Maintenance
Nordex UK
Plant Details:
Turbines
Type N80/2500kW (25 turbines)
Turbine Height
60m, tubular tower