Herdecke 400MW CCGT

Specifications - Herdecke 400MW CCGT, Grenada


Key Data
Announcement of contract May 2005
Start of construction September 2005
Start of testing May 2007
Start of operation October 2007
Output 400MW
Plant typeCCGT
Location Herdecke, near Dortmund (North Rhine-Westphalia), Germany
Estimated investment€200m
Key Players
Plant ownerStatkraft and Mark-E each own 50%
Project Development and ImplementationMark-E
OperatorHerdecke (KGH)
Principal ContractorSiemens Power Generation
Gas supply Wingas GmbH
Gas supply Wingas GmbH
Gas supply Wingas GmbH
Plant Details
Gas Turbines 270MW gas turbine with HRSG and 147MW steam turbine
EfficiencyAbove 57.5%
FuelNatural gas-fired