Key Data:
Total installed capacity
1,320MW
Location
Jorf Lasfar, Morocco
Estimated investment
$1.5 billion
Unit 3 completion
June 2000
Unit 4 completion
December 2000 (operation started October 2001)
Key Players:
Sponsors
CMS Generation Company, ABB
Implementing agency
The Jorf-Lasfar Energy Company (JLEC)
Plant Details:
Units
Two additional 348MW steam turbine generator sets (four in total)
Additional equipment
Two coal-fired boilers, control system and ancillary equipment
Fuel
4 million tons of coal per year