Key Data:
Announcement of Contract
July 2005
Construction Started
Summer 2005
Start of Operation
Summer 2007
Location
Knapsack Chemiepark, near Cologne in North Rhine-Westphalia, Germany
Estimated investment
Around €400m (NOK3.2bn)
Key Players:
Project Management
Helmut Hermanns
Plant Details:
Equipment Supplied
Two 270MW gas turbines, one 260MW steam turbine, three generators and electrical, instrumentation and control equipment
Fuel
Gas supplied by Wingas