Key Data:
Announcement of Contract
31 July 2006
Start of Construction
July 2006
Start of Operation
Summer 2009
Location
Campanillas, Malaga, Spain
Estimated Investment
€300m
Employment
500 to 800 jobs during construction, and 35 permanent jobs and 100 indirect jobs on completion
Key Players:
Plant Owner
Gas Natural (operating in Malaga through its distribution company Gas Natural Andalucía)
Construction
Alstom (including civil works, balance of plant and water and gas pipelines)
Operation and Maintenance
Alstom on 12-year contract
Plant Details:
Gas Turbines
GT26 gas turbine, steam turbine, heat recovery steam generator and TOPGAS turbogenerator, all from Alstom