Key Data:
Announcement of contract
May 2005
Start of operation
October 2006
Output
2.25MW (22.5MW total planned)
Location
Power brought ashore at Agucadoura, northern Portugal
Estimated investment
$8.2m for the first three machines
Key Players:
Plant owner
Energias de Portugal
Project funding
Portuguese consortium led by Enersis
Design, main contractor
Ocean Power Delivery (OPD)
Module manufacturer
Ross Deeptech
Tube segment manufacturer
Camcal
Plant Details:
Type
Initial stage: three 750kW machines
Construction
Four hinged, cylindrical tube segments
Power generation
Hydraulic rams driving hydraulic motors
Dimensions
Tube segments 120m long, 3.5m wide
Weight
760,000kg (750 tons) fully ballasted