Home > Industry Projects > Combined-Cycle Gas Turbine (CCGT) > Plana del Vent 800MW CCGT, Tarragona
Specifications - Plana del Vent 800MW CCGT, Tarragona , Spain
| Key Data |
| Start of operation | Summer 2007 |
| Output | 800MW |
| Plant type | CCGT |
| Location | Tarragona, Spain |
| Estimated investment | Above €360m |
| Key Players |
| Plant owner | Gas Natural |
| Contractor | General Electric |
| Operation and maintenance | GE |
| Subcontractor | UTE (Union Temporal de Empressa), mechanical and electrical balance of plant, civil work, local transportation, erection and commissioning support |
| Plant Details |
| Gas Turbines | Two GE Frame 9FB turbines |
| Combustor | DLN 2.0+ Dry Low NOx |
| Other equipment | Two steam turbines and generators, two HRSGs and integrated control system from GE |
| Efficiency | Around 58% net |
| Fuel | Natural gas primary fuel, gas oil as backup |