Riverside Resource Recovery Facility, United Kingdom




Key Data


The Riverside Resource Recovery facility (RRR) is a UK energy recovery plant under construction at Belvedere in the London Borough of Bexley. The recovery facility is an energy from waste (EfW) plant. Cory Environmental and Riverside Resource Recovery are developing the facility together.

The new energy recovery facility is scheduled to come online in mid 2011. The plant will generate energy that will be adequate to power 66,000 homes, by processing 585,000t of residual waste generated in the region.

The project was proposed to develop an alternative to the Cory's Mucking Landfill site, as it was to be decommissioned in 2010. The facility aims to smooth the transition from landfill to waste treatment.

EfW project history

The proposal for the development of the EfW plant dates back to early 1990s, however, it was cancelled due to technical issues relating to road access and the size of the plant.

Riverside Resource Recovery submitted new proposals to Department of Trade and Industry (DTI) in 1999. The new proposals involved the development of a river-served EfW plant with a capacity of more than 50MW. The development process was objected to and prolonged by the London Borough of Bexley, former Mayor of London Ken Livingstone and other groups. DTI called two further public inquiries in 2003 and 2005 respectively.

The construction of the plant was finally permitted by the secretary of state for trade and industry in June 2006.

"The Riverside Resource Recovery plant will generate energy that will be adequate to power 66,000 homes."

A judicial review challenge to forbid the approval of the project was posted by the mayor of London; however, the two applications were rejected in February 2007.

Riverside Resource Recovery facility Technology

The Riverside Resource Recovery facility will incorporate a waste treatment technology known as incineration. Incineration involves combustion of organic materials and substances to generate heat, which will in turn be used to produce power. It also converts waste into bottom ash, flue gases and particulates.

The waste will be initially combusted in the combustion units of the power plant. The process will be monitored to ensure that minimum combustion temperatures exceed 850°C. High-efficiency boilers will be used to recover the heat energy from the flue gases. The heat energy will be further converted into electric power through the use of steam turbines. The turbine at the facility will be capable of generating 30MW of steam or heat energy and up to 72MW of electricity.

Finance and contracting

The project has received £470m funding under a loan facility by the Bank of Ireland, Barclays Capital and Calyon as the joint lead arrangers. In addition, the project an equity finance of about £80m has been arranged by Cory.

Cory has chosen Von Roll Inova (VRI) as the engineering, procurement and construction (EPC) partner for the project in February 2007. The technology that will be integrated in the energy recovery plant will be provided and installed by VRI. VRI is also responsible for providing operational and maintenance services to the plant for the first four years from the beginning of operations.

VRI elected Costain the civil engineering contractor for the project at the end of 2007.

RRR plant details

The facility is being developed on 6ha of land on the south bank of the River Thames. The site was formerly used for Borax works (a chemical plant). RRR will be capable of processing 585,000t of waste a year. The facility is a river-served recovery plant. The waste to be processed by the plant will be transported by barges and tugs. Cory has commissioned four new Shoalbuster 2208 tugs for the facility.

The waste collected from households and businesses in central London will be processed by RRR. The plant will also receive waste from four Western Riverside Waste Authority (WRWA) boroughs and the City of London. These arrangements will supply about 60% of the waste required by the plant, while the remainder will be delivered by London boroughs and other commercial waste contracts.

Construction

Investigation work on the site began in spring 2007. It was further followed by archaeological and site remediation work.

"The Riverside Resource Recovery facility will incorporate a waste treatment technology known as incineration."

Construction work on the project began in early 2008. It involved reconstruction of Norman Road, the highway to the development site. The development of Norman Road was completed in July 2008 and the highway development work was carried out by the contractor Breheny.

The construction of the RRR facility began in 2008, following the completion of Norman Road improvement works. The construction work included piling of the jetty. The steel used in the construction of the facility is supplied by Bourne Construction Engineering under a supply contract awarded in November 2008.

Bourne is also engaged in erecting the steel structures of the facility. The construction of the entire facility is expected to be completed by mid-2011.

Distribution

About 6MW of the total power that will be generated by the EfW plant will go in captive consumption. The remaining power will be supplied to the power grid. The power will be initially generated at 11kV and further, the voltage will be stepped up to 132kV to export power to the power grid.

Riverside Resource Recovery Facility The Riverside Resource Recovery facility (RRR) is a UK energy recovery plant under construction at Belvedere in the London Borough of Bexley.
Map of Riverside Resource Recovery Facility The Riverside Resource Recovery facility is being developed on 6ha of land on the south bank of the River Thames.
Turbine Converting Steel Enegry The heat energy created by the Riverside Resource Recovery facility will be further converted into electric power through the use of steam turbines.