Home > Industry Projects > Combined-Cycle Gas Turbine (CCGT) > AES Parana Combined Cycle Gas Turbine Plant
Specifications - AES Parana Combined Cycle Gas Turbine Plant, San Nicolas, Argentina
| Key Data |
| Start | 1997 |
| Plant type | Combined Cycle Gas Turbine (CCGT) |
| Location | San Nicolas, Argentina |
| Estimated investment | $439 million |
| Completion | 2001 |
| Power | 830MW |
| Key Players |
| Sponsor | AES Parana (a subsidiary of the AES Group) |
| Finance | Bank of Tokyo (lead bank), IDB, Jexim |
| Lead equipment supplier | Mitsubishi |
| Finance | Bank of Tokyo (lead bank), IDB, Jexim |