Key Data:
Planning application submitted
May 2006
Planning application approved
August 2007
Start of operation
Planned for 2010
Plant type
CCGT (Combined Cycle Gas Turbine)
Location
Newport, South Wales, UK
Estimated investment
£400m ($795m)
Employment
More than 650 jobs during construction and 45 longer-term jobs
Key Players:
Plant owner
Severn Power Ltd (owned by Carron Energy)
Engineering, procurement and construction company
Siemens AG
Plant Details:
Arrangement
Two generating units, each with a gas turbine, waste heat recovery boiler and steam turbine