Enea Polaniec Signs Contract with Sirius Engineering Consortium
Enea Polaniec has selected Sirius Engineering to construct its hydrocyclone installations for gypsum slurry and...
Based on the wet limestone process, the Janikowo FGD Plant was handed over to the client CIECH Soda Polska S.A. on 1 June 2018.
The FGD plant is serving 2 OP-140 Boilers #4 and #5. This is second small-scale limestone wet scrubber completed successfully, demonstrating that wet limestone method is competitive also for such small-sized plants. The speciality of this FGD plant is that it is able to use adjacent semi-dry FGD end product as a ‘free of charge’ reagent and can transform its hazardous end product to commercial grade gypsum.
Sirius Engineers was acting as EPC-manager (EPCM) for Finnish technology provider Valmet Technologies OY.
Enea Polaniec has selected Sirius Engineering to construct its hydrocyclone installations for gypsum slurry and...
Sirius Engineers Ltd provides engineering, procurement and construction management (EPCM) for projects in the fields of...
The Inowroclaw FGD final acceptance protocol has been signed on 7 December 2017. Previous critical...
The Aghios Dimitrios service agreement between J&P Avax and Sirius Engineers was signed on 9...