Waldeck is a 990MW hydro power project. It is planned on Edersee Lake river/basin in Hesse, Germany. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the partially active stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in 1932. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Data Insights Waldeck

Buy the Profile

Data Insights

The gold standard of business intelligence.

Find out more

Description

The project is being developed and currently owned by Uniper. The company has a stake of 100%.

Waldeck is a pumped storage project. The hydro reservoir capacity is planned to be 4.4 million cubic meter.

Waldeck (Waldeck II Plus) consists of 1 unit of pump turbine with 300MW nameplate capacity.

Development status

Post completion of the construction, the project is expected to get commissioned in 1932.

Contractors involved

Waldeck (Waldeck I ) will be equipped with Voith Hydro Holding francis turbines. The phase consists of 4 turbines with 35MW nameplate capacity.

Waldeck (Waldeck I Expansion) will be equipped with Voith Hydro Holding francis turbines. The phase consists of 2 turbines with 35MW nameplate capacity.

Waldeck (Waldeck II) will be equipped with Andritz Hydro francis turbines. The phase consists of 2 turbines with 240MW nameplate capacity.

Voith Hydro Holding will supply electric generator(s) for the Waldeck (Waldeck I ).

Voith Hydro Holding will supply electric generator(s) for the Waldeck (Waldeck I Expansion).

Voith Hydro Holding is expected to supply electric generator(s) for the Waldeck (Waldeck II). The generator capacity is likely to be 265 MVA.

For more details on Waldeck, buy the profile here.

About Uniper

Uniper SE (Uniper), an energy company, which generates, trades and markets energy; and procures, stores, transports and supplies commodities such as LNG, natural gas, coal and energy-related products. The company produces electricity using coal, hydro, nuclear, biomass, wind, solar and other sources. Uniper also produces steam and compressed air and delivers them to industry customers, and heat to households; and offers risk management solutions. The company operates in Europe and other regions; and has power generation facilities in the UK, Germany, Russia, Sweden, the Netherlands and Hungary. Uniper is headquartered in Dusseldorf, Nordrhein-Westfalen, Germany.

This content was updated on 10 July 2024

Data Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.