Adani Green Energy KREDL Solar PV Park-8 is a 25.2MW solar PV power project. It is located in Karnataka, India. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in January 2018.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Solar PV | 25.2 | 25.2 | – | Active | Karnataka, India | Adani Green Energy (UP) |
---|
Description
The project was developed by Adani Green Energy (UP). The project is co-owned by Adani Green Energy and Total Solar Singapore, with their respective ownership stake of 50% each.
Adani Green Energy KREDL Solar PV Park-8 is a ground-mounted solar project.
The project cost is $25.206m.
Development Status
The project got commissioned in January 2018.
Power Purchase Agreement
The power generated from the project is sold to Chamundeshwari Electricity Supply under a power purchase agreement. The power is sold at the rate of $0.073kWh for a period of 25 years, starting from 2018. The contracted capacity is 20MW.
About Adani Green Energy (UP)
Adani Green Energy (UP) Ltd (Adani Green Energy) is a renewable energy company. It constructs, operates and maintains hybrid power projects, utility-scale grid connected solar power plants, wind plants and solar parks. The company is headquartered in India.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.