Alvarez Condarco is a 50.7MW hydro power project. It is located on Mendoza river/basin in Mendoza, Argentina. The project is currently active. It has been developed in single phase. The project commenced construction in 2002.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 50.7 | 50.7 | – | Active | Mendoza, Argentina |
---|
Description
Alvarez Condarco is a run-of-river project. The gross head of the project is 84.5m. The project generated 259 GWh of electricity.
The nameplate capacity of electric generator(s) installed at the site is 17.9 MVA.
The nameplate capacity of electric generator(s) installed at the site is 28.5 MVA.
Development Status
The project commenced construction in 2002.
Contractors Involved
IMPSA was selected as the turbine supplier for the hydro power project. The company provided 1 unit of francis turbine with 15MW nameplate capacity.
IMPSA was selected as the turbine supplier for the hydro power project. The company provided 2 units of francis turbines, each with 23.3MW nameplate capacity.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.