Artemovskaya Cogeneration Plant is a 400MW coal fired power project. It is located in Primorsky Krai, Russia. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in November 1936.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 400 | 400 | – | Active | Primorsky Krai, Russia |
---|
Description
The project is currently owned by Far Eastern Generation.
It is a Steam Turbine with Cogen power plant.
The project generated 2,207,000MWh of electricity.
Development Status
The project got commissioned in November 1936.
Contractors Involved
Leningradsky Metallichesky Zavod was selected as the turbine supplier for the Coal fired project. The company supplied K-100-90, T-87-90 model steam turbines for the project.
NPO Elsib supplied TVF-100-2, Hydrogen Cooled electric generator for the project.
Sibenergomash supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.