Receive our newsletter – data, insights and analysis delivered to you
  1. Market Data
January 11, 2022

Brownsville Combustion Turbine Plant, US

By Carmen

Brownsville Combustion Turbine Plant is a 460MW gas fired power project. It is located in Tennessee, the US. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in June 1999.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 460 460 Active Tennessee, the US

Description

The project is currently owned by Tennessee Valley Authority with a stake of 100%.

It is a Gas Turbine with Cogen power plant that is used for Peakload. The fuel is procured from ANR Pipeline Company.

The project generated 152,714MWh of electricity.

Development Status

Content from our partners
Green investment: What gives Scotland multiple advantages
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration

The project got commissioned in June 1999.

Contractors Involved

SNC-Lavalin Group was selected to render EPC services for the gas fired power project.

Brownsville Combustion Turbine Plant (Brownsville Combustion Turbine Plant Unit I) is equipped with Siemens SGT6-3000E gas turbine. The phase consists of 1 gas turbine with 112MW nameplate capacity.

Brownsville Combustion Turbine Plant (Brownsville Combustion Turbine Plant Unit II) is equipped with Siemens SGT6-3000E gas turbine. The phase consists of 1 gas turbine with 112MW nameplate capacity.

Brownsville Combustion Turbine Plant (Brownsville Combustion Turbine Plant Unit III) is equipped with Siemens SGT6-3000E gas turbine. The phase consists of 1 gas turbine with 118MW nameplate capacity.

Brownsville Combustion Turbine Plant (Brownsville Combustion Turbine Plant Unit IV) is equipped with Siemens SGT6-3000E gas turbine. The phase consists of 1 gas turbine with 118MW nameplate capacity.

Siemens Energy supplied electric generator for the Brownsville Combustion Turbine Plant (Brownsville Combustion Turbine Plant Unit I).

Siemens Energy supplied electric generator for the Brownsville Combustion Turbine Plant (Brownsville Combustion Turbine Plant Unit II).

Siemens Energy supplied electric generator for the Brownsville Combustion Turbine Plant (Brownsville Combustion Turbine Plant Unit III).

Siemens Energy supplied electric generator for the Brownsville Combustion Turbine Plant (Brownsville Combustion Turbine Plant Unit IV).

Innovative Steam Technologies supplied steam boiler for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies