Carreau Manceau is a 32.45MW onshore wind power project. It is located in Hauts-de-France, France. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 2016.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Onshore | 32.45 | 32.45 | – | Active | Hauts-de-France, France | wpd |
---|
Description
The project was developed by wpd.
The Carreau Manceau (Carreau Manceau- Phase 1), has 108m high towers.
The Carreau Manceau (Carreau Manceau- Phase 2), has 104m high towers.
The Carreau Manceau (Carreau Manceau_III), has 108m high towers.
Development Status
The project is currently active. The project got commissioned in 2016.
Contractors Involved
Carreau Manceau (Carreau Manceau- Phase 1) is equipped with Enercon E-82 E2 / 2,000 kW turbines. The phase consists of 8 turbines with 2MW nameplate capacity.
Carreau Manceau (Carreau Manceau- Phase 2) is equipped with Enercon E-92 / 2,350 kW turbines. The phase consists of 5 turbines with 2.35MW nameplate capacity.
Carreau Manceau (Carreau Manceau_III) is equipped with Enercon E-92 / 2,350 kW turbines. The phase consists of 2 turbines with 2.35MW nameplate capacity.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.