Cedegolo is a 72MW hydro power project. It is located on Oglio, Val Rabbia, Remulo, Val Zazza, Poglia river/basin in Lombardy, Italy. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. Post completion of construction, the project got commissioned in 1950. Buy the profile here.

Smarter leaders trust GlobalData

Report-cover

Premium Insights Cedegolo

Buy the Profile

Premium Insights

The gold standard of business intelligence.

Find out more

Description

The project is currently owned by Electricite de France with a stake of 97.4%.

Cedegolo is a reservoir based project. The penstock length is 321m. The penstock diameter is 3.5m.

The hydro power project consists of 3 turbines, each with 24.4MW nameplate capacity.

The hydro power project consists of 2 turbines, each with 0.425MW nameplate capacity.

The project has 2 electric generators installed at the site. The generator capacity is 0.6 MVA.

The project has 3 electric generators installed at the site. The generator capacity is 29 MVA.

Development status

The project got commissioned in 1950.

For more details on Cedegolo, buy the profile here.

This content was updated on 4 January 2024

Premium Insights

From

The gold standard of business intelligence.

Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.