Chamundeswari Biomass Power Plant is a 26MW biopower project. It is located in Karnataka, India. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in April 2008.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Biopower | 26 | 26 | – | Active | Karnataka, India |
---|
Description
The project is currently owned by Sri Chamundeswari Sugars.
The project cost is $40.938m.
Chamundeswari Biomass Power Plant is a combined heat and power (CHP) project. Bagasse is used as a feedstock to power the project.
Development Status
The project got commissioned in April 2008.
Contractors Involved
Shin Nippon Machinery was selected as the steam turbine supplier for the project. The company provided 1 turbine with 26MW nameplate capacity.
Thermax Babcock & Wilcox supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.