Cogollos is a 50MW onshore wind power project. It is located in Castile and León, Spain. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 2010.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Onshore | 50 | 50 | – | Active | Castile and León, Spain | Enel Green Power Espana SLU; Productor Regional de Energia Renovable |
---|
Description
The project was developed by Enel Green Power Espana SLU and Productor Regional de Energia Renovable. The project is currently owned by Enel Green Power Espana SLU.
The project generates 140,000MWh electricity and supplies enough clean energy to power 51,000 households, offsetting 104,000t of carbon dioxide emissions (CO2) a year.
Development Status
The project is currently active. The project got commissioned in December 2010.
Contractors Involved
Siemens Gamesa Renewable Energy was selected as the turbine supplier for the wind power project. The project consists of 25 units of G87-2.0 MW turbines, each with 2MW nameplate capacity.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.