Combigolfe Combined Cycle Power Plant is a 435MW gas fired power project. It is located in Provence-Alpes-Cote dAzur, France. The project is currently active. It has been developed in single phase. The project construction commenced in 2008 and subsequently entered into commercial operation in 2010.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 435 | 435 | – | Active | Provence-Alpes-Cote dAzur, France |
---|
Description
The project is currently owned by Engie with a stake of 100%.
It is a Combined Cycle Gas Turbine (CCGT) power plant.
The project cost is $505m.
Development Status
The project construction commenced in 2008 and subsequently entered into commercial operation in 2010.
Contractors Involved
GE Power was selected to render EPC services for the gas fired power project.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of GT26 gas turbine.
GE Power was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of STF15C steam turbine.
GE Power supplied TOPGAS electric generator for the project.
GE Power supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.