Crossdykes Wind Farm is a 48MW onshore wind power project. It is located in Scotland, the UK. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in a single phase. The project construction commenced in 2019 and subsequently entered into commercial operation in June 2021. Buy the profile here.
Description
The project is developed and owned by Muirhall Energy. The company has a stake of 100%.
The project generates 15,400MWh electricity and supplies enough clean energy to power 44,792 households, offsetting 70,000t of carbon dioxide emissions (CO2) a year.
The Lattice towers installed at the project site are 110m high.
Development status
The project is currently active. The project construction commenced in 2019 and subsequently entered into commercial operation in June 2021.
Power purchase agreement
The power generated from the project is sold to Limejump under a power purchase agreement, starting from 2021.
See Also:
Contractors involved
Nordex was selected as the turbine supplier for the wind power project. The company provided 10 units of N133/4.8 turbines, each with 4.8MW nameplate capacity.
Nordex is the O&M contractor for the wind power project. The operation and maintenance contract commenced from 2021, for a period of 20 years.
For more details on Crossdykes Wind Farm, buy the profile here.
About Muirhall Energy
Muirhall Energy Ltd is a Alternative Energy company that provides renewable and Green Energy services. The company is headquartered in South Lanarkshire, Lancashire, The U.K.
Premium Insights
From
The gold standard of business intelligence.
Blending expert knowledge with cutting-edge technology, GlobalData’s unrivalled proprietary data will enable you to decode what’s happening in your market. You can make better informed decisions and gain a future-proof advantage over your competitors.