Duke Energy-Twenty Nine Palms Solar PV Park is a 26.67MW solar PV power project. It is located in California, the US. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in June 2013.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Solar PV 26.67 26.67 Active California, the US Solar Electric Solutions

Description

The project was developed by Solar Electric Solutions. Duke Energy Renewables and Manulife Financial are currently owning the project having ownership stake of 51% and 49% respectively.

Duke Energy-Twenty Nine Palms Solar PV Park is a ground-mounted solar project.

The project supplies enough clean energy to power 4,000 households.

Development Status

The project got commissioned in June 2013.

Power Purchase Agreement

The power generated from the project is sold to Southern California Edison under a power purchase agreement for a period of 20 years, starting from 2013.

Contractors Involved

SolarWorld Industries was selected to render EPC services for the solar PV power project.

SolarWorld Industries was selected as the supplier of the PV modules for the project. The company installed 100,188 modules at the site.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.