Fortis Coaldale 254S DER Solar PV Park 3 is a 22MW solar PV power project. It is planned in Alberta, Canada. The project is currently in permitting stage. It will be developed in single phase. The project construction is likely to commence in 2022 and is expected to enter into commercial operation in March 2023.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Solar PV 22 22 Permitting Alberta, Canada Acestes Ventures; Concord Green Energy

Description

The project is being developed by Acestes Ventures and Concord Green Energy. The project is currently owned by Concord Green Energy.

Fortis Coaldale 254S DER Solar PV Park 3 is a ground-mounted solar project which is planned over 150 acres.

The project cost is expected to be around $28.27m.

The solar power project consists of 95,000 modules, each with 365W nameplate capacity.

11 inverters are likely to get installed at the project site.

Development Status

The project construction is expected to commence from 2022. Subsequent to that it will enter into commercial operation by March 2023.

Contractors Involved

Gp Joule Canada and Spark Power are expected to render EPC services for the solar PV power project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.