Ganda is a 60MW hydro power project. It is located on Bondone and Caronella river/basin in Lombardy, Italy. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 1955.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 60 | 60 | – | Active | Lombardy, Italy |
---|
Description
The project is currently owned by Edison with a stake of 100%.
Ganda is a reservoir based project. The project generated 104.197 GWh of electricity.
The hydro power project consists of 2 turbines, each with 32MW nameplate capacity.
Development Status
The project got commissioned in 1955.
Contractors Involved
Ercole Marelli Power supplied 2 electric generators for the project. The generator capacity is 30 MVA.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.