Global 3 Escatron Combined Cycle Power Plant is a 285MW gas fired power project. It is located in Aragon, Spain. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in November 2007.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 285 285 Active Aragon, Spain

Description

The project is currently owned by Ignis Generacion with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant that is used for Peakload. The fuel is procured from Enagas SA.

The project cost is $268.761m.

Development Status

The project got commissioned in November 2007.

Contractors Involved

Tecnicas Reunidas was selected to render EPC services for the gas fired power project.

The Gas fired project have been supplied by GE Power and Siemens.

The electric generators for the project were procured from GE Power and Siemens.

Innovative Steam Technologies supplied steam boiler for the project.

Ignis Energia is the O&M contractor for thermal power project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.