Grizzly Wind Farm is an 80MW onshore wind power project. It is planned in Montana, the US. The project is currently in permitting stage. It will be developed in single phase. Post completion of the construction, the project is expected to get commissioned in 2023.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Onshore | 80 | – | 80 | Permitting | Montana, the US | Optimum Renewables |
---|
Description
The project is being developed by Optimum Renewables and is currently owned by Building Energy Holding US.
The project cost is expected to be around $121.9m.
Development Status
Post completion of the construction, the project is expected to get commissioned in 2023.
Power Purchase Agreement
The power generated from the project will be sold to NorthWestern under a power purchase agreement. The power will be sold at the rate of $0.021kWh for a period of 15 years. The capacity to be procured is 80MW.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.