Hawkeye Wind Farm is a 37.5MW onshore wind power project. It is located in Iowa, the US. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in October 2012.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Onshore | 37.5 | 37.5 | – | Active | Iowa, the US | RPMA Wind Development |
---|
Description
The project was developed by RPMA Wind Development. The project is currently owned by BlackRock with a stake of 90% and Renewable Power Markets Access.
The project supplies enough clean energy to power 12,000 households, offsetting 60t of carbon dioxide emissions (CO2) a year. The project cost is $81.338m.
The project has 100m high towers.
Development Status
The project is currently active. The project got commissioned in October 2012.
Power Purchase Agreement
The power generated from the project is sold to Central Iowa Power Cooperative under a power purchase agreement with a contracted capacity is 37.5MW.
Contractors Involved
Nordex was selected to render EPC services for the wind power project.
Nordex was selected as the turbine supplier for the wind power project. The company provided 15 units of N100 (2.5 MW) turbines, each with 2.5MW nameplate capacity.
Nordex is the O&M contractor for the wind power project for a period of 12 years.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.