Hibbing Biomass Power Plant is a 20MW biopower project. It is located in Minnesota, the US. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 2007.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Biopower | 20 | 20 | – | Active | Minnesota, the US |
---|
Description
The project is currently owned by Laurentian Energy Authority.
The project cost is $58.308m.
Hibbing Biomass Power Plant is a combined heat and power (CHP) project. Wood waste which is a kind of wood by-product is used as a feedstock to power the project.
Development Status
The project got commissioned in 2007.
Power Purchase Agreement
The power generated from the project is sold to Xcel Energy under a power purchase agreement for a period of 20 years.
Contractors Involved
Sumitomo SHI FW Energia supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.