Itaipu-Paraguay is a 7,000MW hydro power project. It is located on Parana river/basin in Alto Parana, Paraguay. The project is currently active. It has been developed in single phase. The project construction commenced in 1975 and subsequently entered into commercial operation in 1984.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 7,000 | 7,000 | – | Active | Alto Parana, Paraguay |
---|
Description
The project is currently owned by Itaipu Binacional with a stake of 100%.
Itaipu-Paraguay is a run-of-river project. The hydro reservoir capacity is 29,000 million cubic meter. The gross head of the project is 120m. The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, are 20 in number. The penstock length is 142.2m. The penstock diameter is 10.5m. The project cost is $19,600m.
The hydro power project consists of 10 turbines, each with 700MW nameplate capacity.
Development Status
The project construction commenced in 1975 and subsequently entered into commercial operation in 1984.
Contractors Involved
Voith Hydro Holding supplied electric generator(s) for the project. The generator capacity is 737 MVA.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.