Jebba is a 578.4MW hydro power project. It is located on Niger river/basin in Kwara, Nigeria. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in 1983.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 578.4 578.4 Active Kwara, Nigeria Mainstream Energy Solutions; RusHydro International

Description

The project was developed by Mainstream Energy Solutions and RusHydro International. The project is currently owned by Mainstream Energy Solutions.

Jebba is a run-of-river project. The hydro reservoir capacity is 3,900 million cubic meter. The net head of the project is 27.6m. The total number of penstocks, pipes or long channels that carry water down from the hydroelectric reservoir to the turbines inside the actual power station, are 6 in number. The penstock diameter is 10m.

Development Status

The project got commissioned in 1983.

How well do you really know your competitors?

Access the most comprehensive Company Profiles on the market, powered by GlobalData. Save hours of research. Gain competitive edge.

Company Profile – free sample

Thank you!

Your download email will arrive shortly

Not ready to buy yet? Download a free sample

We are confident about the unique quality of our Company Profiles. However, we want you to make the most beneficial decision for your business, so we offer a free sample that you can download by submitting the below form

By GlobalData
Visit our Privacy Policy for more information about our services, how we may use, process and share your personal data, including information of your rights in respect of your personal data and how you can unsubscribe from future marketing communications. Our services are intended for corporate subscribers and you warrant that the email address submitted is your corporate email address.

Contractors Involved

Andritz Hydro was selected as the turbine supplier for the hydro power project. The project consists of 6 units of Propeller turbines, each with 96.4MW nameplate capacity.

Hitachi supplied 4 electric generators for the Jebba (Jebba_2G1,2G2,2G3,2G5). The generator capacity is 119 MVA.

Hitachi Mitsubishi Hydro supplied 1 electric generator for the Jebba (Jebba_2G4). The generator capacity is 119 MVA.

Hitachi supplied 1 electric generator for the Jebba (Jebba_2G6). The generator capacity is 119 MVA.

RusHydro International is the O&M contractor for the hydro power project.

About Mainstream Energy Solutions

Mainstream Energy Solutions Ltd. (Mainstream Energy Solutions) is a hydroelectric power generation plant. The Company generates electricity and sells it to distributors. It is headquartered in Abuja, Nigeria.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.