Kvarnsveden Mill Plant G21 is a 15MW biopower project. It is located in Dalarna, Sweden. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in July 1953.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Biopower 15 15 Active Dalarna, Sweden

Description

The project is currently owned by Stora Enso.

The project generates 70GWh of electricity.

Wood by-product is used as a feedstock to power the project.

Development Status

The project got commissioned in July 1953.

Contractors Involved

Siemens was selected as the steam turbine supplier for the project. The company provided 1 turbine with 15MW nameplate capacity.

Sumitomo SHI FW Energia supplied steam boiler for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.