Leini Power Plant is a 393.5MW gas fired power project. It is located in Piedmont, Italy. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in 2007.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 393.5 | 393.5 | – | Active | Piedmont, Italy |
---|
Description
The project is currently owned by Engie Italia with a stake of 100%.
It is a CCGT with Cogen power plant.
The project cost is $308.689m.
Development Status
The project got commissioned in 2007.
Contractors Involved
Ansaldo Energia was selected to render EPC services for the gas fired power project.
Ansaldo Energia was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of AE94.3A gas turbine with 265MW nameplate capacity.
Ansaldo Energia was selected as the turbine supplier for the Gas fired project. The company provided 1 unit of RT20 steam turbine with 128.5MW nameplate capacity.
Ansaldo Energia supplied WX21Z-092LLT, Air-Cooled electric generator for the project.
Ansaldo Energia supplied WY23Z-109LL, Air-Cooled electric generator for the project.
AC Boilers supplied steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.