Metiskow 648S DER Solar PV Park is a 22.5MW solar PV power project. It is planned in Alberta, Canada. The project is currently in permitting stage. It will be developed in single phase. The project construction is likely to commence in 2022 and is expected to enter into commercial operation in November 2023.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Solar PV | 22.5 | – | 22.5 | Permitting | Alberta, Canada | Aura Power Renewables; Eridani |
---|
Description
The project is being developed by Aura Power Renewables and Eridani. The project is currently owned by Eridani.
Metiskow 648S DER Solar PV Park is a ground-mounted solar project which is planned over 134 acres.
The project cost is expected to be around $28.913m.
The solar power project consists of 47,372 modules, each with 530W nameplate capacity.
6 inverters are likely to get installed at the project site.
Development Status
The project construction is expected to commence from 2022. Subsequent to that it will enter into commercial operation by November 2023.
About Aura Power Renewables
Aura Power Renewables is a Energy Utility & Services Provider company, It is a solar EPC and development specialist. The company is headquartered in Vancouver, British Columbia, Canada.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.