Narela Waste to Energy Plant is a 24MW biopower project. It is located in NCT, India. The project is currently active. It has been developed in single phase. Post completion of construction, the project got commissioned in March 2017.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Biopower | 24 | 24 | – | Active | NCT, India | Ramky Enviro Engineers |
---|
Description
The project is developed and owned by Ramky Enviro Engineers.
The project cost is $58.111m.
The process of combustion has been adopted in this combined heat and power (CHP) project to release the stored energy from the feed. Refuse which is a kind of municipal solid waste is used as a feedstock to power the project.
The project consists of 1 turbine with 24MW nameplate capacity.
Development Status
The project got commissioned in March 2017.
Contractors Involved
Chongqing Sanfeng Covanta Environmental Industry supplied steam boiler for the project.
About Ramky Enviro Engineers
Ramky Enviro Engineers, Ltd. is a waste management company. It is engaged in waste management covering industrial, municipal and bio medical wastes. It operates as a subsidiary of Hyderabad-based Ramky Group. It has 12 subsidiaries, executing 28 projects across 28 locations in India, West Asia and Singapore.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.