Naro-Fominsk Waste to Energy Power Plant is a 70MW biopower project. It is planned in Moscow, Russia. The project is currently in permitting stage. It will be developed in single phase. Post completion of the construction, the project is expected to get commissioned in 2022.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Biopower | 70 | – | 70 | Permitting | Moscow, Russia |
---|
Description
Gazprombank, RT Invest and Vnesheconombank are currently owning the project.
The project cost is expected to be around $178.518m.
The process of combustion will be adopted in this project to release the stored energy from the feed. Refuse which is a kind of municipal solid waste will be used as a feedstock to power the project.
Development Status
Post completion of the construction, the project is expected to get commissioned in 2022.
Contractors Involved
Atomenergomash will be the steam turbine supplier for the project.
Atomenergomash is likely to be the supplier of the steam boiler for the project.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.