Nihuil I is a 74.24MW hydro power project. It is located on Atuel river/basin in Mendoza, Argentina. The project is currently active. It has been developed in single phase. The project construction commenced in 1942 and subsequently entered into commercial operation in 1957.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 74.24 74.24 Active Mendoza, Argentina

Description

The project is currently owned by Pampa Energia with a stake of 100%.

Nihuil I is a reservoir based project. The gross head of the project is 189m. The penstock length is 347m. The penstock diameter is 4m. Nihuil I underwent through rehabilitation & modernization during 2000. The project generated 365 GWh of electricity.

Development Status

The project construction commenced in 1942 and subsequently entered into commercial operation in 1957.

Contractors Involved

Ansaldo Energia was selected as the turbine supplier for the hydro power project. The company provided 4 units of francis turbines, each with 18.56MW nameplate capacity.

Ansaldo Energia supplied 4 electric generators for the project. The generator capacity is 23.2 MVA.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.