Nine Mile Point Combined Cycle Plant, US

By Carmen

Nine Mile Point Combined Cycle Plant is a 649.5MW gas fired power project. It is located in Louisiana, the US. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 2014.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 649.5 649.5 Active Louisiana, the US

Description

The project is currently owned by Entergy Louisiana with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant.

The project cost is $655m.

Development Status

Content from our partners
Green investment: What gives Scotland multiple advantages
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration

The project got commissioned in December 2014.

Power Purchase Agreement

The power generated from the project is sold to Entergy New Orleans under a power purchase agreement with a contracted capacity is 112MW.

Contractors Involved

Chicago Bridge & Iron and McDermott International were selected to render EPC services for the gas fired power project.

Nine Mile Point Combined Cycle Plant (Nine Mile Point Combined Cycle Plant Unit I) is equipped with GE Power 7F.04 gas turbine. The phase consists of 1 gas turbine with 194.7MW nameplate capacity.

Nine Mile Point Combined Cycle Plant (Nine Mile Point Combined Cycle Plant Unit II) is equipped with GE Power 7F.04 gas turbine. The phase consists of 1 gas turbine with 194.7MW nameplate capacity.

Nine Mile Point Combined Cycle Plant (Nine Mile Point Combined Cycle Plant Unit III) is equipped with Toshiba Energy Systems and Solutions TCDF 33.5 steam turbine. The phase consists of 1 steam turbine with 260.1MW nameplate capacity.

GE Power supplied electric generator for the Nine Mile Point Combined Cycle Plant (Nine Mile Point Combined Cycle Plant Unit I).

GE Power supplied electric generator for the Nine Mile Point Combined Cycle Plant (Nine Mile Point Combined Cycle Plant Unit II).

Toshiba Energy Systems and Solutions supplied electric generator for the Nine Mile Point Combined Cycle Plant (Nine Mile Point Combined Cycle Plant Unit III).

Vogt Power International supplied steam boiler for the project.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU