Osne Plain Wind Park is a 31.8MW onshore wind power project. It is located in Grand Est, France. The project is currently active. It has been developed in single phase. The project construction commenced in 2019 and subsequently entered into commercial operation in June 2020.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Onshore | 31.8 | 31.8 | – | Active | Grand Est, France | Calyce Developpement; TTR Energy |
---|
Description
The project is developed by Calyce Developpement and TTR Energy. These companies also have ownership stakes in the project.
The project cost is $55.253m.
The project has 87m high towers.
Development Status
The project is currently active. The project construction commenced in 2019 and subsequently entered into commercial operation in June 2020.
Contractors Involved
Siemens Gamesa Renewable Energy was selected as the turbine supplier for the wind power project. The company provided 12 units of SG 2.6-126 turbines, each with 2.65MW nameplate capacity.
About Calyce Developpement
Calyce Developpement SAS (Calyce Developpement) provides wind farms services. The company is located in France.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.