Pamukoren Geothermal Power Plant, Turkey

By Carmen

Pamukoren Geothermal Power Plant is a 144.5MW geothermal power project. It is located in Aydin, Turkey. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in October 2013.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Geothermal 144.5 144.5 Active Aydin, Turkey Celikler Yatirim Holding

Description

The project is developed and owned by Celikler Yatirim Holding.

The geothermal plant is of binary type.

Development Status

The project got commissioned in October 2013.

Content from our partners
Green investment: What gives Scotland multiple advantages
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration

Contractors Involved

Atlas Copco was selected to render EPC services for the Pamukoren Geothermal Power Plant (Pamukoren Geothermal Power Plant Unit I & II) project. Atlas Copco was selected to render EPC services for the Pamukoren Geothermal Power Plant (Pamukoren Geothermal Power Plant Unit III) project. Atlas Copco was selected to render EPC services for the Pamukoren Geothermal Power Plant (Pamukoren Geothermal Power Plant Unit IV) project. Atlas Copco was selected to render EPC services for the Pamukoren Geothermal Power Plant (Pamukoren Geothermal Power Plant Unit V) project.

Pamukoren Geothermal Power Plant (Pamukoren Geothermal Power Plant Unit I & II) is equipped with Atlas Copco Inflow Radial Turbine turbines. The phase consists of 2 turbines with 22.5MW nameplate capacity.

Pamukoren Geothermal Power Plant (Pamukoren Geothermal Power Plant Unit III) is equipped with Exergy turbine. The phase consists of 1 turbine with 22.5MW nameplate capacity.

Pamukoren Geothermal Power Plant (Pamukoren Geothermal Power Plant Unit IV) is equipped with Exergy turbine. The phase consists of 1 turbine with 22.5MW nameplate capacity.

About Celikler Yatirim Holding

Celikler Yatirim Holding AS operates in the sectors such as construction-contractual works (Ready concrete), Mining, Tourism and Energy. The company is headquartered in Ankara, Turkey.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU