Evrencik Wind Farm is a 129.6MW onshore wind power project. It is planned in Kirklareli, Turkey. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the partially active stage. It will be developed in multiple phases. The project construction is likely to commence in 2020 and is expected to enter into commercial operation in 2020. Buy the profile here.
Description
The project is being developed by Evrencik Ruzgar Enerjisinden Elektrik Uretim Ltd. Sti. The project is co-owned by RES Anatolia Holding and STFA Yatirim Holding, with their respective ownership stake of 50% each.
The project is expected to generate 534,000MWh of electricity. The project cost is expected to be around $132.81m.
The Evrencik Wind Farm (Evrencik Wind Farm Phase I), will have 125m high towers.
The Evrencik Wind Farm (Evrencik Wind Farm Phase II), will have 125m high towers.
Development status
The project construction is expected to commence from 2020. Subsequent to that it will enter into commercial operation by 2020.
Contractors involved
Nordex will be the turbine supplier for the wind power project. The project consists of 27 units of N149/4.0-4.5 turbines, each with 4.8MW nameplate capacity.
Nordex is expected to perform operations and maintenance for the Evrencik Wind Farm (Evrencik Wind Farm Phase I). The operation and maintenance contract tenure will likely be commencing from 2020, for a period of 15 years.
Nordex is expected to perform operations and maintenance for the Evrencik Wind Farm (Evrencik Wind Farm Phase II) for a period of 15 years.
For more details on Evrencik Wind Farm, buy the profile here.