Higashi Niigata Thermal Power Plant Unit III & IV is a 2,873MW gas fired power project. It is located in Niigata, Japan. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in December 1984. Buy the profile here.

Description

The project is currently owned by Tohoku Electric Power with a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant.

Development status

The project got commissioned in December 1984.

Contractors involved

Mitsubishi Power was selected to render engineering procurement construction services for the gas fired power project.

Higashi Niigata Thermal Power Plant Unit III & IV (Higashi Niigata Thermal Power Plant Unit III & IV Phase III Block I) is equipped with Mitsubishi Power steam turbine. The phase consists of 1 steam turbine with 203MW nameplate capacity.

Higashi Niigata Thermal Power Plant Unit III & IV (Higashi Niigata Thermal Power Plant Unit III & IV Phase III Block I) is equipped with Mitsubishi Power M701D gas turbines. The phase consists of 3 gas turbines with 137MW nameplate capacity.

Higashi Niigata Thermal Power Plant Unit III & IV (Higashi Niigata Thermal Power Plant Unit III & IV Phase III Block II) is equipped with Mitsubishi Power steam turbine. The phase consists of 1 steam turbine with 203MW nameplate capacity.

Higashi Niigata Thermal Power Plant Unit III & IV (Higashi Niigata Thermal Power Plant Unit III & IV Phase III Block II) is equipped with Mitsubishi Power M701D gas turbines. The phase consists of 3 gas turbines with 137MW nameplate capacity.

Higashi Niigata Thermal Power Plant Unit III & IV (Higashi Niigata Thermal Power Plant Unit III & IV Phase IV Block I) is equipped with Mitsubishi Power steam turbine. The phase consists of 1 steam turbine with 265MW nameplate capacity.

Higashi Niigata Thermal Power Plant Unit III & IV (Higashi Niigata Thermal Power Plant Unit III & IV Phase IV Block I) is equipped with Mitsubishi Power M701G gas turbines. The phase consists of 2 gas turbines with 270MW nameplate capacity.

Higashi Niigata Thermal Power Plant Unit III & IV (Higashi Niigata Thermal Power Plant Unit III & IV Phase IV Block II) is equipped with Mitsubishi Power steam turbine. The phase consists of 1 steam turbine with 272MW nameplate capacity.

Higashi Niigata Thermal Power Plant Unit III & IV (Higashi Niigata Thermal Power Plant Unit III & IV Phase IV Block II) is equipped with Mitsubishi Power M701G gas turbines. The phase consists of 2 gas turbines with 284MW nameplate capacity.

Mitsubishi Power supplied Horizontal-Shaft Tubular Rotary Field Type electric generator for the project.

Mitsubishi Power supplied steam boiler for the project.

For more details on Higashi Niigata Thermal Power Plant Unit III & IV, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.