Quest Solar PV Park is a 53.3MW solar PV power project. It is planned in South Carolina, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in a single phase. The project construction is likely to commence in 2025 and is expected to enter into commercial operation in June 2026. Buy the profile here.

Description

The project is being developed by Quest Solar and is currently owned by Southern Current with a stake of 100%.

Quest Solar PV Park is a ground-mounted solar project which is planned over 300 acres.

The project cost is expected to be around $53.833m.

The solar power project consists of 5,600 modules, each with 340W nameplate capacity.

20 inverters are likely to get installed at the project site.

Development status

The project construction is expected to commence from 2025. Subsequent to that it will enter into commercial operation by June 2026.

For more details on Quest Solar PV Park, buy the profile here.

GlobalData

GlobalData, the leading provider of industry intelligence, provided the underlying research used to produce this article.

This information is drawn from GlobalData’s Power Intelligence Center, which provides detailed profiles of over 170,000 active, planned and under construction power plants worldwide from announcement through to operation across all technologies and countries worldwide.