The Renovo Energy Center is 1,026MW gas fired power project. It is planned in Pennsylvania, the US. According to GlobalData, who tracks and profiles over 170,000 power plants worldwide, the project is currently at the permitting stage. It will be developed in multiple phases. Post completion of the construction, the project is expected to get commissioned in April 2023. Buy the profile here.

Description

The project is being developed and currently owned by Renovo Energy Center. The company has a stake of 100%.

It is a Combined Cycle Gas Turbine (CCGT) power plant. The power plant can run on dual-fuel. The primary fuel being used to power the plant will be natural gas. In case of shortage of natural gas the plant will run on Hydrogen.

The project cost is expected to be around $750m.

The Gas fired project consists of 2 gas turbines.

The Gas fired project consists of 2 steam turbines.

Development status

Post completion of the construction, the project is expected to get commissioned in April 2023.

For more details on Renovo Energy Center, buy the profile here.