Priest Rapids, US

By Carmen

Priest Rapids is a 955.6MW hydro power project. It is located on Columbia river/basin in Washington, the US. The project is currently active. It has been developed in single phase. The project construction commenced in 1956 and subsequently entered into commercial operation in 1959.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Hydropower 955.6 955.6 Active Washington, the US

Description

The project is currently owned by Public Utility District No. 2 of Grant County.

The project generated 3,885.193 GWh of electricity.

Development Status

The project construction commenced in 1956 and subsequently entered into commercial operation in 1959.

Content from our partners
Green investment: What gives Scotland multiple advantages
How Hengst helped to keep Germany’s charity “star singers” shining
How one power station prevented frequent shutdowns with three-stage air filtration

Power Purchase Agreement

Avista, Eugene Water & Electric Board, PacifiCorp, Portland General Electric, Public Utility District No. 1 of Cowlitz County, Puget Sound Energy, Seattle City Light and Tacoma Water are the power offtakers from the project.

Contractors Involved

The English Electric was selected as the turbine supplier for the hydro power project. The company provided 8 units of kaplan turbines, each with 95MW nameplate capacity.

The English Electric was selected as the turbine supplier for the hydro power project. The company provided 2 units of kaplan turbines, each with 97.8MW nameplate capacity.

The English Electric supplied 2 electric generators for the project.

The English Electric supplied 8 electric generators for the project. The generator capacity is 86 MVA.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.

Related Companies

NEWSLETTER Sign up Tick the boxes of the newsletters you would like to receive. The top stories of the day delivered to you every weekday. A weekly roundup of the latest news and analysis, sent every Wednesday. The power industry's most comprehensive news and information delivered every month.
I consent to GlobalData UK Limited collecting my details provided via this form in accordance with the Privacy Policy
SUBSCRIBED

THANK YOU