The Sam Bertron Combined Cycle Power Plant is 823MW gas fired power project. It is planned in Texas, the US. The project is currently in permitting stage. It will be developed in single phase. The project construction is likely to commence in 2022 and is expected to enter into commercial operation in 2024.

Project Type Total Capacity (MW) Active Capacity (MW) Pipeline Capacity (MW) Project Status Project Location Project Developer
Thermal 823 823 Permitting Texas, the US NRG Texas Power

Description

The project is being developed and currently owned by NRG Texas Power.

It is a combined cycle gas turbine (ccgt) power plant.

The project cost is expected to be around $1,144.217m.

The Gas fired project consists of 1 steam turbine.

The Gas fired project consists of 2 gas turbines, each with 255MW nameplate capacity.

Development Status

The project construction is expected to commence from 2022. Subsequent to that it will enter into commercial operation by 2024.

Methodology

All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.