Sango is a 68.8MW hydro power project. It is located on Agano river/basin in Fukushima, Japan. The project is currently active. It has been developed in multiple phases. The project construction commenced in 1939 and subsequently entered into commercial operation in 1943.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Hydropower | 68.8 | 68.8 | – | Active | Fukushima, Japan |
---|
Description
The project is currently owned by Tohoku Electric Power.
The hydro reservoir capacity is 7.591 million cubic meter.
Sango (Sango 2) consists of 1 turbine with 23.7MW nameplate capacity.
Sango (Sango 1) consists of 3 units of kaplan turbines.
The project consists of 4 generators.
Development Status
The project construction commenced in 1939 and subsequently entered into commercial operation in 1943.
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.