Sichuan Guangan Power Generation Plant is a 2,400MW coal fired power project. It is located in Sichuan, China. The project is currently active. It has been developed in multiple phases. Post completion of construction, the project got commissioned in October 1999.
Project Type | Total Capacity (MW) | Active Capacity (MW) | Pipeline Capacity (MW) | Project Status | Project Location | Project Developer | Thermal | 2,400 | 2,400 | – | Active | Sichuan, China |
---|
Description
The project is currently owned by Sichuan Guangan Power Generation with a stake of 100%.
It is a steam turbine power plant.
Development Status
The project got commissioned in October 1999.
Contractors Involved
Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase I Unit I) is equipped with Dongfang Turbine N300-16.7/537/537-5 steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase I Unit II) is equipped with Dongfang Turbine N300-16.7/537/537-5 steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase II Unit I) is equipped with Dongfang Turbine N300-16.7-537/537-8 steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase II Unit II) is equipped with Dongfang Turbine N300-16.7-537/537-8 steam turbine. The phase consists of 1 steam turbine with 300MW nameplate capacity.
Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase III Unit I) is equipped with DEC Dongfang Steam Turbine N600-16.7 / 538 / 537-1 steam turbine. The phase consists of 1 steam turbine with 600MW nameplate capacity.
Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase III Unit II) is equipped with DEC Dongfang Steam Turbine N600-16.7 / 538 / 537-1 steam turbine. The phase consists of 1 steam turbine with 600MW nameplate capacity.
DEC Dongfang Electric Machinery supplied QFSN-300-2-20 electric generator for the Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase I Unit I).
DEC Dongfang Electric Machinery supplied QFSN-300-2-20 electric generator for the Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase I Unit II).
DEC Dongfang Electric Machinery supplied QFSN-300-2-20 electric generator for the Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase II Unit I).
DEC Dongfang Electric Machinery supplied QFSN-300-2-20 electric generator for the Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase II Unit II).
DEC Dongfang Electric Machinery supplied QFSN-600-2-22C electric generator for the Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase III Unit I).
DEC Dongfang Electric Machinery supplied QFSN-600-2-22C electric generator for the Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase III Unit II).
Dongfang Boiler Group supplied steam boiler for the Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase I Unit I).
Dongfang Boiler Group supplied steam boiler for the Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase I Unit II).
Dongfang Boiler Group supplied steam boiler for the Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase II Unit I).
Dongfang Boiler Group supplied steam boiler for the Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase II Unit II).
Dongfang Boiler Group supplied steam boiler for the Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase III Unit I).
Dongfang Boiler Group supplied steam boiler for the Sichuan Guangan Power Generation Plant (Sichuan Guangan Power Generation Plant Phase III Unit II).
Methodology
All power projects included in this report are drawn from GlobalData’s Power Intelligence Center. The information regarding the project parameters is sourced through secondary information sources such as electric utilities, equipment manufacturers, developers, project proponent’s – news, deals and financial reporting, regulatory body, associations, government planning reports and publications. Wherever needed the information is further validated through primary from various stakeholders across the power value chain and professionals from leading players within the power sector.